At this evenings Norwood Forum AGM there was a brief presentation and update from the PictureHouse Cinemas group and Lambeth Council regarding the project. During the discussion it became clear that the planning application is due to be put before planning in roughly two weeks time.
There will then be an 8 week period of engagement before the steering group committee come to form its own conclusion in October 2015. This in turn would lead to a 5-6 month period of more detailed design work. Building on the site would therefore not really begin until around May 2016 and will take roughly a year to build.
We’ll look to keep you updated but if you hear anything please do not hesitate to contact us.